Filed: May 24, 2018
Opinion by: Judge McDonald
Holding:
Maryland courts interpreting
construction contracts under Virginia law will first look to the contract
language and then to parol evidence to determine the intent of the parties
regarding whether a construction subcontract contains a pay-when-paid or
pay-if-paid clause.
Facts:
George Mason University (“Owner”) hired
Dustin Construction (“General Contractor”) to renovate the school’s student union
building, and General Contractor hired Young Electrical (“Subcontractor”) for
the electrical work.
The Subcontract contained a
provision “Contractor’s obligation to pay … Subcontractor … is contingent, as
a condition precedent, upon Contractor’s receipt of payment from
the Owner…” (Section 2(c)).
Subcontractor submitted cost
increase requests to General Contractor, which submitted cost increase requests
to Owner. Owner rejected the request;
General Contractor never paid the additional cost to Subcontractor. Subcontractor sued General Contractor for
breach of contract. The Circuit Court
for Montgomery County granted General Contractor’s motion for summary judgment. Subcontractor appealed.
Analysis:
“Contract interpretation is
governed by the law of the place of contract or the law chose by the parties.” Cunningham v. Feinberg, 441 Md. 310, 326 (2015). However, the standard for summary judgment is governed by the law of the forum, in this case Maryland law. Goodwich v. Sinai Hosp. of Baltimore, Inc., 343 Md. 185, 204-207 (1996). Under the Maryland Rules, a circuit court may grant summary judgment only if there is no genuine dispute as to any material fact, and the moving party is entitled to judgment as a matter of law. Maryland Rule 2–501(f).
The Virginia Supreme Court has
referenced Maryland law in examining the issue in this case. The Maryland Court of Appeals relied on a 1962
Sixth Circuit case (Thos. J. Dyer Co. v.
Bishop Int’l. Engineering Co.) when it examined the issue in Atl. States Const. Co. v. Drummond & Co.
(1968) and Fishman Constr. Co. v.
Hansen (1965). In Maryland, Conditional
Payment provisions are to be construed as timing provisions (pay-when-paid
clauses) unless the contract language clearly indicates that the parties
intended the clause to be a condition precedent (pay-if-paid clause). The Special Court of Appeals had affirmed
the Circuit Court’s decision. It held
that Section 2(c) contained the “magic phrase” “condition precedent”.
The Court considered whether the General Contractor was entitled to summary judgment for the reason given by the Circuit Court and concluded it was not, then went through an analysis of the reason for summary judgement originally argued by the General Contractor.
No comments:
Post a Comment
Please Post Comments Here