Filed: July 28, 2017
Opinion by: Judge Adkins
Holding:
A surety
company that guarantees performance of a construction subcontract with a performance
bond is not bound by the subcontract’s mandatory arbitration clause when the subcontract
is incorporated by reference into the bond and the clause refers only to the subcontract’s
parties and the bond allows for dispute resolution in court.
Facts:
In May 2009, Plaintiff, a construction
contractor, signed a Master Subcontract Agreement (“MSA”) with NCS, an
electrical subcontractor, to cover future projects. The MSA included a mandatory arbitration
clause (the “Clause”). In October 2009, Plaintiff
was hired by another construction contractor to help build a medical research
facility. Plaintiff in turn hired NCS to
help with the project. Plaintiff and NCS
signed a subcontract (“NCS Subcontract”) that incorporated the MSA by
reference. The NCS Subcontract required
NCS to furnish a performance bond (“Bond”), which it obtained from
Defendant. The Bond made NCS and
Defendant jointly and severally liable to Plaintiff for performance of the NCS
Subcontract.
During construction, a dispute
arose, NCS abandoned the site and Plaintiff terminated the contract. In February 2014, Plaintiff filed a demand
for arbitration with NCS. In April 2014,
Plaintiff amended the demand to include Defendant. Defendant filed a petition in Howard County
Circuit Court in which it requested a declaratory judgment that it was not
bound by the Clause.
The case was transferred to a more
proper venue, Harford County Circuit Court, which granted partial summary
judgment for Defendant. That court explained
that the Bond is only insuring that Defendant is liable for any construction
that has not been performed, and found no evidence of an intention that Defendant should be bound to
dispute resolution provisions of the MSA.
The Court of Special Appeals
affirmed, holding that “the ‘joint and several’ obligation clause in the (Bond)
does not evince (Defendant’s) assent to be bound by the (Clause) in the
incorporated-by-reference chain of documents.”
Schneider Elec. Bldgs. Critical
Sys., v. Western Sur. Co., 231 Md. App. 27, 46 (2016). The Court of Appeals granted Plaintiff’s
petition for a writ of certiorari.
Analysis:
The Court of Appeals applied
Maryland contract law to determine if Defendant is bound by the Clause. Precedent in Maryland requires courts to look
at the intention of the parties as expressed in the language of the
contracts. The Court of Appeals
explained in Hartford Accident &
Indem. Co. v. Scarlett Harbor Assocs., 346 Md. 122, 127 (1997) that “arbitration
is a process whereby parties voluntarily
agree to substitute a private tribunal for the public tribunal otherwise
available to them” and an arbitration clause “cannot impose obligations on
persons who are not a party to it and do not agree to its terms.”
The Court of Appeals interpreted
the Bond by “constru(ing) (the Bond, NCS Subcontract, and MSA) as a whole…not
(by) read(ing) each clause or provision (of each contract) separately.” Owens-Illinois
v. Cook, 386 Md. 468, 497 (2005).
Here, the Court of Appeals agreed
with the lower courts because the Clause refers to the “parties” to the NCS
Subcontract (which are Plaintiff and NCS) and the Bond permits court actions to
resolve disputes between NCS and Defendant.
Since Defendant was not a “party” to the NCS Subcontract, the Clause
does not apply to Defendant. The Court
of Appeals found support in its holding in Liberty
Mutual Insurance v. Mandaree Public School District #36, 503 F.3d 709 (8th Cir.
2007), whose facts are similar to this case.
The full opinion is available PDF.
No comments:
Post a Comment
Please Post Comments Here